Home 
Planning the build
 
Why build an extension?
 
Initial design sketches
 
On-line Building Regs
 
Meeting planners
 Meeting building control
 Planning the foundations
 Planning the floor slab
 Marking out the footings
 Damp proof course issues
 Possible drainage problems?

 Construction of the walls
 Proposed roof structure
Windows diary
 Window challenges
 Initial window plans
 Making the casements
 Making the frame
 Designing leaded lights
 Making leaded lights
 Assembling the window
 The little window

 The door frame
Demolition diary
 The demolition starts!
 The demolition continues
 Still more demolition

Foundations diary
 Foundation issues
 Drain issues
 Digging the foundations
 Rethinking foundations!
 Pouring the foundations

Floor slab diary
 Rethinking the slab!
 Floor vent extensions
 Preparing the slab #1
 Preparing the slab #2
 Pouring the slab

Walls diary
 Preparing to build walls
 Build up to the DPC
 Build the walls #1
 Build the walls #2
 The gas men cometh
 Build the walls #3
 Finishing the walls
Roof diary
 Roof structure build
 Tiling the roof
 Finishing the roof
 Finishing the gables
 Roof insulation
 Guttering

Internals
 Floor screed
 Plumbing
 Electrics
 Shower room
 Shower room floors
 Shower room walls
 Utility room
 Utility room walls
 Utility room floor
 Finishing the windows

Project finished!
 Final inspection
 The certificate
 Final thoughts

 Twelve months on!
Out-takes!
 Mistakes
Costs
 Material costs
Links
 Links
Sister sites
 House re-roof project
 Home gas usage data

 Stop paint flaking
 DIY secondary glazing
 gare.co.uk

 


Building the roof structure
 
 

I've started planning the roof structure so I went and bought some 100mm by 47mm sawn timber.

I placed the 2.4 metre length on top of the wall to act as the wall plate. I used the 3 metre length (the roof joists will be 150mm by 47mm) to determine the angle of the roof.

The planned angle is 35 degrees , which is about the minimum fall for roof tiles.

I cut a notch out of the roof joist so it rests on the wall plate.

The joist will be cut off - I have marked the wood so that the soffit (the piece of wood on which the gutter is fitted) can be added. The soffit is planned to cover the upper half of the on-end bricks above the window.

Tuesday, 22nd May: I cemented in the additional blocks today to bring the height of the inside wall up to where it should be. All I need do now is to cement down the wall plate. The wall plate needs to be strapped to the inside wall at some stage using metal straps.



Thursday, 24th May:  I demolished the roof above the back door of the house clearing the way to start building the new roof structure.
Building Control visit Stage 8 - wall plate: The Building Regulations Surveyor came at lunch at said that he was happy with the wall construction up to the wall plate.

We discussed the roof and he recommended that I use Tyvek breathable membrane together with 90mm insulation with a 50mm gap between the felt and the top of the insulation - quite easy using 150 x 47mm joists. I would then not need any other vents at the top of the roof or in the eaves.

Friday, 25th May: I fitted the 1 metre wall plate straps - a total of four.


This is a picture of how the existing soffit boards are fitted - I'll do it the same way.
The roofing timbers arrive!
I used 10mm expanding rawlbolts to attached the 100mm by 50mm wall plate. The bolts were spaced at 800mm.


I cut the first 150mm by 50mm roof joist to sit on the wall plate.

The joists are made for building as they are preserved using Tanialith 'e' and strength graded.


Saturday, 25th May: WE started the day by cutting all the tops of the joists.
We laid the joists out on the roof and carefully measured each one to get the wall plate notches in the correct positions.
Cutting the notches is easier using a hand saw.
The notches are pretty good, though I have a few gaps of a few millimetres - and a mistake as can be seen on the outtake page.

All joists now fit spaced at 400mm centre to centre. This is a good width as 1200mm is the width of a plasterboard sheet and it will make the mounting of the ceiling easier.


The last job of the day was to cut the ends of the joists so that the soffit board can be attached. This takes a little care as a mistake can prove to be rather expensive!

I used a line with all the joists in place to make sure that all the ends of the joists are aligned.

The next job is place the horizontal 100mm x 50mm ceiling joists, though the weather forecast is rain tomorrow so I might have to have a day off!

After that I need to block the end eve up to the level of the top of the joists.

Sunday, 27th May: Heavy rain today - the most I've seen since starting the extension. Fortunately I can now place a tarpaulin over the joists to keep the rain out.
Just realised That I have made my first bad mistake.

Halfway along the roof the wall indents by 130mm. This means that the joists are longer and should be higher by around 60mm in that depth. However, I've placed the wall plate at the same height which is wrong.

I need to raise the wall plate here by 60mm and replace the joists. What a pain!

I moved the wall plate.
I've mounted the lower wall plate to hold the ceiling rafters.
Monday, 28th May: I put in most of the ceiling rafters today, though I need to buy three more joists tomorrow before I can do any more.

It's been pouring with rain all day but at least with the tarpaulin up I can do all the roof work in the dry.
They all seem to be level and at the same height!
Close up of the coach screws I used to connect the ceiling rafters to the roof joists.
The right-angle brackets I used to connect the ceiling rafters to the wall pate.

I used screws where there is a pulling force of the rafters.
Tuesday, 29th May: I finished fitting the rest of the roof joists today - 13 in total.
I added 'noggins' 550mm noggins between the joists and added joist hangers to the bottom of the joist to fix them in place on the wall plate.


Eying along the roof, they all seem to be in alignment since I moved the wall plate up that I screwed to the wall in the wrong place.



I can now call in the Building regulations Surveyor and block in the gable end ready for tiling.

I went to my local reclaim supplier and chose the tiles I will use. I plan to pick these up on Thursday after I've picked up the 25 x 38mm tile batons (which are spaced at 100mm) and the soffit board.

Wednesday, 30th May: The weather has been awful all day - raining. Perhaps I should have taken the day off!

I've spend all day building the gable end of the extension using blocks which will be eventually rendered and painted white.

The outer gable wall is 50mm lower than the inside one so that I can place a length of 50 by 100 mm wood along the top. This will be used to nail the gable soffit board and the tile battons to.

I plan to pick up the 25 by 38mm tile battons and the 900 reclaimed clay roof tiles tomorrow.

Building Control visit Stage 7 - roofing timbers: The Building Control Surveyor came today and OKed the roofing timbers - hooray!

Back to home