Home 
Planning the build
 
Why build an extension?
 
Initial design sketches
 
On-line Building Regs
 
Meeting planners
 Meeting building control
 Planning the foundations
 Planning the floor slab
 Marking out the footings
 Damp proof course issues
 Possible drainage problems?

 Construction of the walls
 Proposed roof structure
Windows diary
 Window challenges
 Initial window plans
 Making the casements
 Making the frame
 Designing leaded lights
 Making leaded lights
 Assembling the window
 The little window

 The door frame
Demolition diary
 The demolition starts!
 The demolition continues
 Still more demolition

Foundations diary
 Foundation issues
 Drain issues
 Digging the foundations
 Rethinking foundations!
 Pouring the foundations

Floor slab diary
 Rethinking the slab!
 Floor vent extensions
 Preparing the slab #1
 Preparing the slab #2
 Pouring the slab

Walls diary
 Preparing to build walls
 Build up to the DPC
 Build the walls #1
 Build the walls #2
 The gas men cometh
 Build the walls #3
 Finishing the walls
Roof diary
 Roof structure build
 Tiling the roof
 Finishing the roof
 Finishing the gables
 Roof insulation
 Guttering

Internals
 Floor screed
 Plumbing
 Electrics
 Shower room
 Shower room floors
 Shower room walls
 Utility room
 Utility room walls
 Utility room floor
 Finishing the windows

Project finished!
 Final inspection
 The certificate
 Final thoughts

 Twelve months on!
Out-takes!
 Mistakes
Costs
 Material costs
Links
 Links
Sister sites
 House re-roof project
 Home gas usage data

 Stop paint flaking
 DIY secondary glazing
 gare.co.uk

 


Final thoughts
 
 

There are a few things that still need to be done like relay the slabs around the edge of the extension but I will do these as and when I find time in coming months.

Looking back, I never really thought that it would take as long as it did even though I was spending significant time on most days - including weekends - on the build. However, I didn't work twelve hours a day!

In general I really enjoyed the build and I was tremendously lucky with the weather in that April was like summer allowing me to get all the foundations, floor slab, walls and roof completed before the bad weather of May, June, Jul and August hit us! I would probably be not so happy if I was held up for weeks because of the weather.

I learnt a lot about building, which was one of the big benefits of undertaking all the work myself. Interestingly, I could not find answers either in books or on the Internet for many of the challenges I faced and I can't praise the local Building Regulations Inspector enough who turned out to be a real help in providing guidance on how to do things. In effect, he acted as a very cheap architect so I would certainly recommend keeping whoever you need to work with on your side.

On reflection, I am pleased to say that there are no major things that I would do differently and I didn't have to do too much remedial work - the door step being one.

I couldn't have undertaken the work without tools and I was pleased that most of the machinery I required I already owned so do not try and save money by not having the right tools or relying on hiring - this could prove to be very expensive indeed.

If you are used to undertaking DIY, are sensible about using tools and willing to take a bit of risk I would advise anyone to have a go. But... Be realistic on the time it will actually take you to complete, especially if you need to hold down a full-time job as well. In that case I would imagine that anyone could become bored with the project extending over twelve months even though you could save quite a lot of money.

Good luck with your own venture and let me know how you get on!

Back to home